Supplying plant field selection in PR

Former Member
0 Kudos

Dear All,

i need to make the supplying plant field as an optional field with item category U and document type NB.

any ideas.

reagards

Accepted Solutions (0)

Answers (6)

Answers (6)

Prasoon
Active Contributor
0 Kudos

Hi,

   Go to SE16 and enter the table T162 and maintain the field selection for the field selection key PT7B as shown below:

Mainly check FAUS3.

Regards,

AKPT

Former Member
0 Kudos

Hi AKPT,

I tried with same above settings, but it is working fine with ME51, but not ME51N.

Prasoon
Active Contributor
0 Kudos

Hi,

   Did you check the field selection key AKTH also in the path:OLME -  Purchase Requisition - Define Screen Layout at Document Level.?

   Please check the same for the field selection keys PT7B & ME51N

Regards,

AKPT

Former Member
0 Kudos

Hi AKPT,

Could you please provide me the screenshot for the same how it has to be as i didnot change for AKTH.

Thank you in advance..

Regards

Sesha.

Former Member
0 Kudos

Hi,

For ME51N, it is by default the Supplying plant field is Optional, then i changed in PT7B, the Supplying plant as Optional. Then it is working fine with ME51, but not in ME51N

Prasoon
Active Contributor
0 Kudos

Hi,

   For AKTH, you can maintain it in config level in the path: OLME -  Purchase Requisition - Define Screen Layout at Document Level.

Regards,

AKPT

Former Member
0 Kudos

same here but it is only working with t code me51 not with me51n

Former Member
0 Kudos

Hi AKTH,

Unfortunately, I donno it is going for dump when i try to select AKTH and the program is getting terminated. But i could able to see or modify the details in ME51N and PT7B. But when I click select AKTH and click on details, program is getting terminated and is going for dump.

Former Member
0 Kudos

Hi Kamal,

Yes, if you change the settings in Field selection group PT7B to Optional, It works. But it works with ME51 but not ME51N.

Former Member
0 Kudos

Yes it will work for ME51 T-code and not for ME51N

Former Member
0 Kudos

Go to SPRO—MM—Purchasing--Purchase Requisitions--Define Screen Layout at Document Level > Here For Field Selection Key  ME51N—goto--Supplying Plant—Make the field as Optional

Former Member
0 Kudos

already done but still have an error also i made it optional in all field selection keys

Former Member
0 Kudos

Hi, If your are selecting the Item category as U , then you need to enter the supplying source for which you want to create the STO PR.

former_member183424
Active Contributor
0 Kudos

That is not a business logic.

If you are using item category U, then the supplying plant have to be entered.

Its a mandatory field.

Former Member
0 Kudos

but this special case and asked by my customer the supplying plant will be determined during the creation of the PO

Prasoon
Active Contributor
0 Kudos

Hi,

   I checked the settings and its working fine for me:

   Only difference could be that I'm in ME51.

Regards,

AKPT

former_member183424
Active Contributor
0 Kudos

I hope you have to maintain the supplying plant in the case of item category U in PR.

Put the supplying plant as a initial.

Then when you make the PO from PR, then you can change the Supplying plant in PO.

No issues for that.

former_member183424
Active Contributor
0 Kudos

Yes..

It can happens through ME51 not in ME51N.

Former Member
0 Kudos

i'm already made this setting and assign NBB field selection key to the document type and also in NBB i made the supplying plant optional and still not working

Prasoon
Active Contributor
0 Kudos

Hello,

   I'm able to create PR with item cat U and without supplying plant in ME51N also:

Regards,

AKPT

Former Member
0 Kudos

could u tell me what in the setting you have done related to the document type and field selection key

Prasoon
Active Contributor
0 Kudos

Hi,

  Go to OLME -  Purchase Requisition - Define Screen Layout at Document Level. Here select the Field selection group PT7B and go to details. Here, you can maintain the field selection as optional entry as shown below:

Regards,

AKPT

Former Member
0 Kudos

i'm already made this settings but still when i creating the PR the supplying plant come mandatory