Hi collegues.

I want to reset actual prices of activities for cost center group. But when I did it I don't have any actual prices for all cost centers. How can I reset prices of activities only for cost centers which include in the cost center groups?

thanks

Add comment
10|10000 characters needed characters exceeded

2 Answers

  • Posted on Dec 13, 2013 at 04:07 PM

    Dear Alexander

    I am not getting your point clearly but what I understood is that you could not get success in resetting Actual Activity Price calculation and you want to reset and recalculate it. Am I right?

    First point is why you want to reset it? If you do this the allocations which have already been done basing existing actual price will be reversed.

    Even then if you want to do this, then go to KSII Select the period to be reset and then got to main menu under EXTRA tab you will find RESET. Click it it will give you warning that by resetting this all allocations will be reversed. Click enter. It is reset now.

    Regards

    Rajneesh Saxena

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Rajneesh Saxena

      Yes. It's not working for cost center group. Activity prices are reseted for all cost centers in controlling aria. But I want to do this for my group only.

  • Posted on Dec 13, 2013 at 04:00 PM

    Hi Alexander.

    Do you try KBK6 to manual set actual activity price?

    Arturo.

    Add comment