on 12-13-2013 7:37 AM
Hi Experts,
I am having a material which is having only one BOM and one routing. Now for this material in the material master in the selection method indicator i have put as 3 as selection only by production version and i have maintained one production versions 1.
I have only maintianed BOM in production version not routing as per screen shot.
Now when I am creating a production order for this material manually through CO01 system is allowing to create production order. when is the selection is only by production version how system is allowing to create production order.
When I go in mater data tab of production order it shows me routing but actually I have not selected any routing in production version.
AS in screen shot
Kindly Help.
Regards,
Sachin
Hello Sachin,
SAP recommends routing allocation in production version as per note 329310 when working with production versions and Routings vary according to the production versions.
The MRP4 view selection method is generally applied for BOM alternative determination. When you do not mention routing in production version, system selects the routing based on OPL8 configuration.
Kindly go through the last section of the link shared below:
Automatically Selecting a Routing (SAP Library - Production Orders (PP-SFC))
The routing selection is based on production version if both the following two conditions are satisfied:
1. You have selection method '3' in MRP4 view.
2. You have routing allocated in the PV.
Otherwise the OPL8 setting is referred.
Best Regards,
Rajen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Sachin,
Check Production version-Automatic/manual options in OPL8, also, check theTasklist tpe selection in OPL8. But the highest Priority is the Selection ID which you have maintained in OPL8.
If You not maintained the TaskList type in this Selection ID, system will throw an error and you cannot able to create an order.
PROD.VER is mandatory for Prodcution Order creation. Anupamji, please correct if I am wrong.
Plz check & Revert.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Subrahmanyam,
When you have multiple PVs then you need to choose manually/automatically which is to be defined mandatory in OPL8 but if you have more than one routing and you are not working with PVs for them then you need to have manual selection in Routing selection as 6 for making routing selection mandatory and manual. Here you can maintain the no selection of routing while creating order.
Check and revert.
Regards,
Anupam Sharma
Hi All,
Thanks for your reply.I understand the concept in OPL8.
But Can you please answer my below question which I already mentioned
If the Production Version has only BOM and no routing (But routing is valid on that perticular date for material), then Production Order is created or not?
If it creates then ok(is it standard behavior)because it is creating in my case or if not then how? .
Regards,
Sachin
Hi
While maintaining the Order type dependent paratemets for your plant and order type combination and select manual selection of Production version and in MRP 4 maintain it only by production version.
Check and revert.
Regards,
Anupam Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Anupam,
Thanks for your reply.
I have maintained and check all setting as you told me but still my purpose is not sloved.
I have not maintained routing in production version 1 but routing is valid on that perticular date
Now I am creating production order by CO01 and it is not giving me error like no valid routing etc,
If I see the master data tab of production order it shows me routing group, counter lot size etc which I mentioned by screen shot in my origional post.
So I just want to know that If the Production Version has only BOM and no routing, then Production Order is created or not?
If it creates then ok(is it standard behavior)or if not then how? because it is creating in my case.
Kindly Help
Regards,
Sachin
Hi
It checks first the routing assigned to PV and copies to production order while creating the order but, if it no there then it will check the routing selection id maintained in OPL8and if you want to check that then maintain 6 in routing selection id which is manually and mandatory selection of routing.
Check and revert.
Regards,
Anupam Sharma
Hi Experts,
Can I get help on this.
Regards,
Sachin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hii Sachin,
I believe,
Since PV is having only BOM and consistent therefore BOM selection in order is happening in satisfaction to you selection method indicator value 3 in MRP4 view of the material.
In OPL8, at plant and order type level, in planning tab, the routing selection setting is enable the auto selection of the only single routing. This has resulted in routing came to order automatically even when same in not selected in order creation.
if you want routings option for manual selection should come whether one or alternative, Please change the routing setting to suitable level in OPL8, Planning tab.
Regards,
User | Count |
---|---|
88 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.