cancel
Showing results for 
Search instead for 
Did you mean: 

Production order should not create without Production Version

Former Member
0 Kudos

Hi Experts,

I am having a material which is having only one BOM and one routing. Now for this material in the material master in the selection method indicator i have put as 3 as selection only by production version and i have maintained one production versions  1.

I have only maintianed BOM in production version not routing as per screen shot.

Now when I am creating a production order for this material manually through CO01 system is allowing to create production order. when is the selection is only by production version how system is allowing to create production order.

When I go in mater data tab of production order it shows me routing but actually I have not selected any routing in production version.

AS in screen shot

Kindly Help.

Regards,

Sachin

Accepted Solutions (1)

Accepted Solutions (1)

former_member208398
Active Contributor
0 Kudos

Hello Sachin,

SAP recommends routing allocation in production version as per note 329310 when working with production versions and Routings vary according to the production versions.

The MRP4 view selection method is generally applied for BOM alternative determination. When you do not mention routing in production version, system selects the routing based on OPL8 configuration.

Kindly go through the last section of the link shared below:

Automatically Selecting a Routing (SAP Library - Production Orders (PP-SFC))

The routing selection is based on production version if both the following two conditions are satisfied:

1. You have selection method '3' in MRP4 view.

2. You have routing allocated in the PV.

Otherwise the OPL8 setting is referred.

Best Regards,

Rajen

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi

If the standard logic described here does not match your business requirements, I suggest you to use BAdI WORKORDER_UPDATE to make your own check for the production version and routing.

BR

Caetano

Former Member
0 Kudos

Hi Rajen/Anupam,

Thanks a lot to both of you.

Your expert advice help me to understand the concept.

Regards

Sachin

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear Sachin,

            Check Production version-Automatic/manual options in OPL8, also, check theTasklist tpe selection in OPL8. But the highest Priority is  the Selection ID which you have maintained in OPL8.

If You not maintained the TaskList type in this Selection ID, system will throw an error and you cannot able to create an order.

PROD.VER is mandatory for Prodcution Order creation. Anupamji, please correct if  I am wrong.

Plz check & Revert.

Anupam1143
Active Contributor
0 Kudos

Hi Subrahmanyam,

When you have multiple PVs then you need to choose manually/automatically which is to be defined mandatory in OPL8 but if you have more than one routing and you are not working with PVs for them then you need to have manual selection in Routing selection as 6 for making routing selection mandatory and manual. Here you can maintain the no selection of routing while creating order.

Check and revert.

Regards,

Anupam Sharma

Former Member
0 Kudos

Dear Anupamji,

               Sry, I could not interpret my point on the above, my query is that, SI it mandatory to have PV while creating the prd Order ??

Regards,

Subrahmanyam B

Former Member
0 Kudos

Hi All,

Thanks for your reply.I understand the concept in OPL8.

But Can you please answer my below question which I already mentioned

If the Production Version has only BOM and no routing (But routing is valid on that perticular  date for material), then Production Order is created or not?

If it creates then ok(is it standard behavior)because it is creating in my case or if not then how? .

Regards,

Sachin

Former Member
0 Kudos

Hi,

IT will be created as per your Selection ID and task list you have selected in OPL8.

As per std settings it will be created, unless you change them as mandatory.

Regards,

Subrahmanyam B

Anupam1143
Active Contributor
0 Kudos

Hi Subrahmanyam,

It is not necessary to give PV while creating Order, the selection of PV in OPL8 works when you are working with PV( Manually/Automatically).

Check the note mentioned by Mr Rajen.

Regards,

Anupam Sharma

Anupam1143
Active Contributor
0 Kudos

Hi

While maintaining the Order type dependent paratemets for your plant and order type combination and select manual selection of Production version and in MRP 4 maintain it only by production version.

Check and revert.

Regards,

Anupam Sharma

Former Member
0 Kudos

Hi Anupam,

Thanks for your reply.

I have maintained and check all setting as you told me but still my purpose is not sloved.

I have not maintained routing in production version 1 but routing is valid on that perticular date

Now I am creating production order by CO01 and it is not giving me error like no valid routing etc,

If I see the master data tab of production order it shows me routing group, counter lot size etc which I mentioned by screen shot in my origional post.

So I just want to know that If the Production Version has only BOM and no routing, then Production Order is created or not?

If it creates then ok(is it standard behavior)or if not then how? because it is creating in my case.

Kindly Help

Regards,

Sachin

Anupam1143
Active Contributor
0 Kudos

Hi

It checks first the routing assigned to PV and copies to production order while creating the order but, if it no there then it will check the routing selection id maintained in OPL8and if you want to check that then maintain 6 in routing selection id which is manually and mandatory selection of routing.

Check and revert.

Regards,

Anupam Sharma

Former Member
0 Kudos

Hi Experts,

Can I get help on this.

Regards,

Sachin

Former Member
0 Kudos

Hii Sachin,

I believe,

Since PV is having only BOM and consistent therefore BOM selection in order is happening in satisfaction to you selection method indicator value 3 in MRP4 view of the material.

In OPL8, at plant and order type level, in planning tab, the routing selection setting is enable the auto selection of the only single routing. This has resulted in routing came to order automatically even when same in not selected in order creation.

if you want routings option for manual selection should come whether one or alternative, Please change the routing setting to suitable level in OPL8, Planning tab.

Regards,