Pull list MF60 genration from planned order

Hi Gurus

I am executing pull list from planned order . it is working fine.

but my client wants to every day update planning table through MF50 &

want to delete planned order created from planning run according to their plan

but when i am trying delete that planned order requirement is going negative. so please put some light on it solve this

Thanks & Regards

Sandeep Kumar Praharaj

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Dec 20, 2013 at 08:49 AM

    HI,

    Planned orders created by the MF50 are firmed planned orders, since these are created manually by the user. If allocation or distribution of the requirement qty is not completely assigned by the user then system will generate the planned order for the remaining qty as per demand entered.

    Ask the user to completely allocate the requirement qty, so negative requirement will be seen.

    Or consider only firmed planned order for the pull list, you can ask the user to go with only the firmed planned orders during pull list creation.

    Since the original question of this thread has been answered, please mark the correct answer in order to close this thread.

    Rgds,

    Abhijit.

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 16, 2013 at 05:43 AM

    Hi Gurus

    Any body pls help how to resolve this?

    Thanks & Regards

    Sandeep Kumar Praharaj

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      System will generate the planned orders based on the requirement only. If you delete the planned orders, then the requirement will show in negative only. That means shortage of the qty. It is the standard behaviour of the system. To meet the shortage system will create the planned order.

      Regards,

      V. Suresh