on 12-11-2013 11:41 AM
Dear Experts,
While Creating Production Order Based Purchase Requisition the Closed Indicator as Assigned.
Due to this Process Problem we cant change the Purchase Order .it shows the Error "
Here i can able to change the same PO via ME22 but unable to change ME22N. I have searched the Related Documents
the founded Reason is the Closed Indicator of Purchase Requisition is flagged.My Requirement is How can i Unflag the Closed indicator.
Here am Raising the Purchase Order Manually via ME21N.
Thanks in Advance..
With Regards,
Thangam.P
Dear Friends,
Still now am facing the same problem. Please anyone suggest me . before creating PO the requisition the Quantities are open. After creating PO the closed indicator assigned default. i think problem is on PO not in Creating requisition.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There are only option to set or remove closed indicator in the PR is ME52N or it will set the closed indicator from ME59N or ME59 (If the option is chosen Set PReqs to "Closed" = 2-Always)
Rest of these two option, I don't think there are any option to set the closed indicator automatically in PR.
And If the closed indicator is set on PR, You are not able to create PO from PR (Whatever the open quantity).
Check this option if you are creating PO via ME59N or ME59.
Did you checked all the fields correctly in delivery tab in PO for PR closed indicator, might be it had been moved some were left side due to some cursor effect.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Perumal,
Its strange...System should allow to remove the closed indicator. Are you able to make any other changes?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I don't know why your system behave like this.
It means if you make a PR of 100 qty.
When you make PO of 100 qty, then your PR is closed.
But if you reduce the quantity of PO via ME22N for 50 qty, then you PR is opened for 50 qty.
Then you can make a new PO for 50 qty.. or can increase the existing PO..
Lets try some different.
Check this..
Change the error message to warning. Then try to change the PO or create a new PO.
I know its little risk.
But just try it yourself.
What the problem you have faced?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I just checked my system and the button is certainly available for the combination of item category L (3) and account assignment F.
Your screen shot shows that the field is hidden in ALV control
In my case it is not hidden.
We have in common that we cannot change the ALV control, you cannot remove it; I tried to set and it did not save.
check how the setting is for your field selection in
OLME > purchase order > Define Screen Layout at Document Level
The indicator is in section Deadline Monitoring
Check this field for all your activities listed and let me know if you have activities where this purchase requisition closed field in not selected at all.
Can we know in which SAP environment your into SAP ECC EHP5?
Also could you check the PO document type config , if any layout is assigned to your PO document type.
Or any screen variant is assigned to your USER role?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Could you please check if any Alternative Uint of measure is maintained in MMR, if so please check the order unit in PR and PO are same or they are different?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Experts,
Please Consider if I create Requisition based on Production Order for
1000 PC. I can able to Raise PO for 1000 PC i clear about it. But My Requirement is
if i Raise PO for 500 PC,remaining 500 PC should be in Open Quantity. I need to Raise Remaining 500 PC for another PO. in this Logic is Working Well for another Customer. In this Problem occurring for new customer. I think the problem Arieses due to configuration settings. Please anyone help me out how to rectify in this problem.
For your information.
PR(Production Order) 10021627 10 - has set the closed indicator, means:
that no further purchase orders are to be created for
this purchase requisition. field EBAN-EBAKZ = X
PO (Purchase Order ) 4500053199 item 10 has set the flag "delivery complete" indicator
field EKPO-ELIKZ = X meaning: Indicates that the item is to be regarded as
closed.
Thank u in Advance.
Regards,
Thangam.P
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As your statement..
We can use the 500 remaining pcs for PO.
There are no configuration about it.
Can you check the PR status
What is the PR quantity and What it shown in Status tab?
See the status
My PR content 1500 pc, I have made 500 BOX of PO (1 BOX = 10 Pcs)
It means my PR order quantity is full.
What about yours?
Hi , closed indicator is never set automatically in PR , for more info refer the below link it may help you..
http://wiki.scn.sap.com/wiki/display/ERPSCM/Closed+Indicator+in+Purchase+Requisition
Hi DEV,
My Problem is
If i Create Purchase order for 1000 PC based on Purchase Requisition the PO is Created.
if i reduced PO quantity as 500 PC system will allows the changes. My Point is Remaining 500PC Open Requisition i may raise Another PO or again i need to Increase the Quantity as 1000 PC for same PO. but in this changes are system not allowed me. if i use same procedure for another customer the changes are allowed. what is the configuration between two customers. What i have to do rectify the Problems.
Regards,
Thangam.P
if you had a requisition of 1000 and ordered 1000, then the requisition is closed, if you reduce the order to 500, then the user will see message 06876 telling him that 500 will be open again.
if the user then clicks the checkered flag (requisition closed) button at the far end of the schedule line (check it in ME23N > item detail > schedule tab) then he intentionally closed the requisition and nothing will stay open.
if your PR is closed, then you can reopen it by clicking this button at the end of the schedule line again
It was clearly explained you in PO line item under Deliver schedule tab , were you can see your purchase requisition and open quantity , beside open quantity you have schedule line after that you can see Preq closed field for which you can flag or Unflag on the square box to make the PR closed indicator ticked automatically.
Once the requested quantity is adopted and procured earlier, why you want to use same PR for PO.
Better raise another request and adopt to create PO which is standard practice.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This error is coming because you have made PO full quantity of PR.
Suppose you make PR of quantity of 10.
Then if you make the PO with quantity 10 from this PR.
After the PO save. When ever you are going to create new PO with reference to this PR or You are trying to increase the existing PO quantity, you will get the message.
This not related closed indicator.
If the reason is Closed indicator then you will get this message
Requisition 10001339 00010 closed
Message no. 06877
Message was edited by: Dev Patra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can un-flag the closed indicator in ME52N.
What do you mean by: While Creating Production Order Based Purchase Requisition the Closed Indicator as Assigned.
Standard SAP does not create 'closed' requisitions from production order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.