How to clean up scheduling agreements with overdelivery

michele_williams
Participant
0 Kudos

My company uses "perpetual" scheduling agreements with our suppliers, often many years old. Historically, we have kept the "unlimited" indicator on for all line items, in order to avoid errors which result from early delivery of schedule lines. Now we would like to become more disciplined and have therefore implemented a user exit which will allow receipts up to 7 days early but stop anything beyond that window. Accordingly we want to un-check "unlimited".

However, due to many years of bad practices, we find that we have a number of line items which have quantities delivered which exceed quantity ordered. Rather than re-check the "unlimited" indicator and remove our new controls, we need a way to clean up these imbalances. Essentially, we would want to set the current ordered quantity to equal delivered quantity as a "true up" and then move forward with our new controls.

Can anyone suggest a way to do this that will not drive additional requirements? Or are we forced to delete this line item and create new ones when we encounter this condition?

Thank you

Michele

Accepted Solutions (0)

Answers (1)

Answers (1)

Prasoon
Active Contributor
0 Kudos

Hi,

   I'm not fully clear about the requirement. As of my understanding, you want to control the open schedule lines. In this case, you may use the tolerance concept during GR for scheduling agreements.

   Here, you may uncheck the unlimitted indicator using mass transaction and then set the tolerance limit for GR against scheduling agreement. For activating the tolerance key for SA, you may need to go for development using the enhancement MEVME001 or EXIT_SAPLEINR_001. You may refer SAP Note 7840 for more details.

   The document explains all the possibilities in detail. Please refer the document.

    If you are talking about scheduling agreements for which the over delivery is already posted, you cant clean it up and match with the ordered quantity.

    If your question is different, please elaborate.

Regards,