Dear Experts,

When I am running deadline monitoring report (ip30) , I have observed that previous date(basic start date) work orders been generated. Please help me to investigate reason behind this . (when i saw report in IW39 by giving created on date as 5/12/2013 , i found that 4 orders were generated having basic start date 3/11/2013 and 6/11/2013)

Hints :

Plan is strategy plan (2 weekly)

call horizon is 50%

"Completion requirement " check box is marked.