Hello gurus,
I got a CTM planning logic concern on how demand is being pegged by CTM run and how it is being prioritized. I know that this can be controlled in CTM settings strategies tab but this sample scenario made me confused...
I have a two demands:
demand 1 = 1000 dated 01.01.2014
demand 2 = 500 dated 03.02.2014
I only have 100 stocks on the week before demand 1.
What I find weird is that after my CTM run, it created Planned Order pegged to demand 2 only.
05.01.2014 = 300 ==> pegged to demand 2
12.01.2014 = 100 ==> pegged to demand 2
19.01.2014 = 100 ==> pegged to demand 2
The one pegged to demand 1 is the remaining stock of 100, which is obviously cannot fulfill it.
My demand prioritization in CTM is Material Availability Date. So in my understanding, CTM should create planned order prioritizing demand 1 since it is the one with earlier MAD.
Is there any other settings that controls this scenario? ALso, can you give me more information how the system would know how it will peg the stocks and planned orders in a demand?
And how they were prioritized?
Thanks in advance!
Ayana Lee
Hi Ayana,
CTM is creating supply for Demand 2 and not Demand 1.
This suggests me two things.
1) In the explanation profile, you said it only shows stock is not available. CTM will try to produce it as next step. But, CTM is not able to find valid source of supply (please check your PDS effective dates)
2) As the demand is close to today's date. CTM is encountering a constraint (May be one of your time fences) because of which CTM is not creating demands.
You can move Demand 1 date in future and try if CTM is creating supply for it. If it does, then it's to do with the SNP production horizon.
Regards,
Abhay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ayana,
From the CTM run results you have got, it looks earliest supply possible is on 5th January 2014( whatever constraints/settings are there).
Since you have not allowed late fulfillment of demand, system is unable to fulfill demand 1.
By allowing Late fulfillment, you should get the desired result.
Of course, you will have consult business if late fulfillment will be okay from business perspective.
Apart from "Allow Late fulfillment of Demand", You may also check the CTM profile setting for Planning Strategies >> Order Creation field ( Order Creation Start ... Days from Today.
As stated in earlier replies, you also need to check Horizons(Production, Stock transfer horizon, Planned delivery time etc.).
regards
Datta
Hi
Is The Demand 1 is not Met ??
Check the Lateness and Earliness settings in CTM Gobal Settings
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Suggest you to activate explanation profile for your CTM run, by which you can have all the information why the demands are not fully fulfilled.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.