on 12-06-2013 1:41 AM
In our current business flow, production order confirmations are most of the time partial and when it is the last operation with PP03 (Auto GR) as control key, quantities are posted equivalent to the yield quantity being confirmed. Now we are being required to post the full GR quantity only on the final confirmation. Is this possible to automate GR only on the final confirmation and how?
Example Order qty: 1000pc, first partial confirmation for operation with PP03 ctrl key = 600 (no GR should be posted here).
Next confirmation for operation with PP03 (final confirmation) = 400 pc (Auto GR here should be 1000pc). Is this possible?
Hi Jorosza,
As per the standard SAP system design it is not possible. You need to post the manual good receipt 101 through MIGO or MB31. For that you have to deactivate auto good receipt from your control key.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
System gives only two options for GR i.e. auto GR ( check setting on OP67) and manual through MIGO. To achieve your scenario in standard, is almost impossible. You can try BADI's as described above
Regards
Qazi Raheel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Algura,
In standard SAP through configuration settings this may not be possible,but you can check using this
BADI (WORKORDER_CONFIRM & WORKORDER_GOODSMVT) to build your logic for confirmation
and goods movement postings.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Jorosza,
I hope it's not the best practice as well as it's not possible. What's the need of this requirement? You register confirmation details but don't want to do GR, for example order qty as 1000 you done confirmation on yesterday with 400 qty and today with 600 qty. As per your statement you have to do GR with today date with the whole qty 1000. What about your production qty with yesterday date? let us know your exact requirement to think about the alternative solution.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ska Ska,
We have to report the production effeciency in real time. If they were able to process in partial, they have to encode yield in partial. However, as per company's requirement, we need to finish the batch in full, not partial, hence the proposal to Post GR only on final confirmation.
Hi,
In standard with auto GR, you cannot declare yield as 400 and expect the system to post GR for 1000 quantities. You can restrict the last operation confirmation to allow only single final confirmation using an exit whereas other operations can be confrmed partially.
Regards,
Ravi Kumar C.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.