Cross System object locking (CSOL)


Hi,

I want to know, if we activate Cross System object locking (CSOL), then do we need to wait till chnages to that particular object is delivered in production ?

I mean other chnages which involve same object changes, do they need to wait till exiting locked object moved to production.

Regards

PK

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 06, 2013 at 02:44 AM

    Hi PK,

    This is depends how you customize it.

    You can do :

    • Send warning message - this means object can saved and imported even if older transport exist and not yet imported to PRD
    • Send Error message - here is not possible to save object till old transport imported to PRD

    By the standard customizing:

    • save 1 object in 2 parallel Urgent Change - error message
    • save 1 object in 1 NC and parallel UC - warning message
    • save 1 object in 1 NC and parallel NC - warning message

    And also you need to consider lock monitor, even if UC is imported to PRD you need to delete locks manually or make project import buffer to PRD, this will refresh all locks.

    Rg Dan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.