Make-to-Stock

28 Views

Dear Export,

Make-to-Stock

In make-to-stock production scenario stock is produced independently of orders because you want to provide your customers immediately with goods from that stock later on. You might even want to produce goods without having sales orders, if you expect that there might be customer demand in the future

Steps in SAP

Create materials with required views - MM01

Maintain CIN master data - J1ID

Create Bill of Materials (BOM) - CS01

Create Routing to Finished material - CA01

Create sale order - VA01

Run MRP - MD50

View the planned orders created - MD04

Convert component planned order to PR (PR will show a/c assgn cat as M) – MD04

Convert semi finished planned order to PR (PR will show a/c assgt cat “M” & item cat. “L”) – MD04

Convert component PR into PO for external procurement - ME21N

Goods receipt with reference to sale order - MIGO

View the stock (sale order stock) - MMBE

Create subcontract PO with reference to semi finished PR - ME21N

Maintain storage location to the subcontractor - SPRO

Transfer goods to Subcontractor (movement type 311 +E) - MB1B / MIGO

Stock will be updated Subcontract storage location under Sale order stock - MMBE

Create challan - J1IFQ

Receive goods from Subcontractor with movt type 101 (543 will be taken to the component & subcontractor storage location to be entered) - MIGO

Reconciliation of challan – J1IFQ

Complete challan – J1IF13

Convert finished material planned order to production order - MD04

Goods issue to the production with movement type 261 - MB1A / MIGO

Confirmation of Production order - CO15

Goods receipt against Production order with movement type 101 - MB31/MIGO

Order settlement for Production order - KO88

Delivery of Finished products - VL01

This is a mm related work or pp work ?