Mass BOM Change(Special procurement field)

Former Member
0 Kudos

Dear Experts,

  How to Enter Special Procurement Field for Components of 1000 BOM's at a time, Please guide me.

Accepted Solutions (0)

Answers (1)

Answers (1)

SR_SAKTHIVEL
Explorer
0 Kudos

Hi,

Use CEWB - Transaction to change BOM in MASS, follow the below steps to get your requirement done.

- Select current work area as Header Change (SAP_BOM) or BOM item Level changes (SAP_ITEM )

- On item tab select the component you want to replace & enter plant

- Select LOAD BOMs & Task list icon.

- System will load all the BOM's that have that item. If a BOM has multiple items with same component number , multiple lines of BOM are displayed.

-  Select the change (Pencil) icon on the screen

- The component columns can now be changed. then insert the new component number for each of the BOM's.

- Hit save icon.

- System will display message work list saved.

Refer Below Link for details.

Starting a Mass Change (SAP Library - BOMs (PP-BD-BOM))

Regards,

Sakthivel SR