Dear Experts,
How to Enter Special Procurement Field for Components of 1000 BOM's at a time, Please guide me.
Hi,
Use CEWB - Transaction to change BOM in MASS, follow the below steps to get your requirement done.
- Select current work area as Header Change (SAP_BOM) or BOM item Level changes (SAP_ITEM )
- On item tab select the component you want to replace & enter plant
- Select LOAD BOMs & Task list icon.
- System will load all the BOM's that have that item. If a BOM has multiple items with same component number , multiple lines of BOM are displayed.
- Select the change (Pencil) icon on the screen
- The component columns can now be changed. then insert the new component number for each of the BOM's.
- Hit save icon.
- System will display message work list saved.
Refer Below Link for details.
Starting a Mass Change (SAP Library - BOMs (PP-BD-BOM))
Regards,
Sakthivel SR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.