cancel
Showing results for 
Search instead for 
Did you mean: 

REL settlement

Former Member
0 Kudos

we have one production order ZP03, we want to settle it during REL, DLV and TECO instead of standard TECO and DLV, is it possible to do so? how to do it?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

HI Siva,

For settlement of production order, DLV or TECO status is mandatory for the production order. If you dont want to activate TECO status then only WIP can be calculated and updated.

Regards,

Ravi Kumar C.