Dear All,
Can you please explain the effect of GI time in SNP and PPDS heuristic with example.
Thanks in advance.
Hi Paul,
GI time is one of buffer time in planning. In intercompany transfer scanerio lead time is calculated as GI + Transportation duration +GR. To calculate GI time, outbound resources needs to be maintained in location master. In case any clarification, do let me know.