IBP Supply with Network without customer

former_member345633
Discoverer
0 Kudos

Hi,

We have business scenario where supply planning starts with demand available at DC level where as standard IBP supply starts with demand at customer level.

Is there way IBP supply can be configured that planning starts with demand at DC level then propogates upstream to supply plants instead of starting at Customer level by default as it does in IBP Standard Model.

Regards,

Manish

Accepted Solutions (1)

Accepted Solutions (1)

former_member242371
Contributor
0 Kudos

Hi Manish,

Yes, you can enter the demand as INDEPENDENTDEMAND which an input kf for supply planning and available at PROD-LOC level.

Please check SAP4 model or help link for details.

Thanks,

Rohit

former_member345633
Discoverer
0 Kudos

Thanks Rohit.