Inspection Lot For Calibration Order in CRTD status

Hi All,

I am creating calibration order through schedule maintanance plan by IP01, IP10, IP30, IP24.

Order is created and inspection lot 14 also generated.

But Inspection lot in CRTD status.

Find Attached document.

Please tell the possible reasons for that

  Thanks,

  Parag

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Nov 23, 2013 at 07:41 AM

    Hi,

    I couldn't find your attachment. However Have you created Task list ?

    If Yes, then Please Check Sampling Procedure attached or not in Characteristic overview, Inspection points 300 (Inspection point for equipment) in Header Screen.

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 23, 2013 at 07:35 AM

    Hi Parag,

    Pl check following,

    1. Make sure maintenance plan is there and equipment is assigned to it.
    2. Inspection char are assigned to your task list

    May also refer following thread for additional reasons and solutions.

    http://scn.sap.com/thread/1053674

    Regards,

    ntn

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Parag,

      As I told before, I have not worked with 14 type too much so really cannot say if sampling procedure is mandatory or not. Yes it does not impact other inspection type you mentioned.

      Still, you can make a sampling procedure with Fixed sample. Maintain sample size as 1 and acceptance number 0. This way there won't be any impact of SP (tick only sampling procedure in the control indicators of MIC)

      Run a case with sampling procedure and let me know.

      Regards,

      ntn

  • avatar image
    Former Member
    Nov 24, 2013 at 07:52 PM

    Try to follow the process flow step by step and check if all prerequisites is as supposed.

    If the status is only showing CRTD then it seems that you have to check if you have released the maintenance order:

    BR

    Erik


    flow.JPG (36.8 kB)
    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 25, 2013 at 08:36 AM

    I oppinion there has been no answer so far. Paraq, you raised an issue, tells that all suggestions has ben done and now you just say it is solved. So what was your reak mistake?
    An inspection lot with status CRTD are not so far in the process, that it is because of a missing selected set - that problem is much later in the proces.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Paraq,

      In the inspection setup of the QM view of the material master, sample determination can be defined in the following ways:

      • Manually
      • Percentage
      • With reference to a sampling procedure

      In your case just select 100% inspection and ensure that the fist characteristic in your inspection plan is required.