When i am trying to link BP to vendor by using the Transaction FLBPC2 system showing an error like"

Business partner  could not be assigned to vendor 
Message No. CVIV_UI020

Do any one know how and why the system is showing this error message

10 |10000 characters needed characters left characters exceeded

Did you follow the procedure suggested by this error message?

0
* Please Login or Register to Answer, Follow or Comment.

2 Answers

avatar image
Former Member Jan 17, 2017 at 04:34 AM
0

Hii,

System not providing any kind of solution in that error message,

I have done all the basic configuration required for integration already.

Regards

Shihab

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Nov 23, 2017 at 07:55 PM
0

Hi,

If there is any error to Link Existing BP to Existing Vendor as below, go to BP T code with Change mode and try to save the BP,it might have some field which was optional at the time of CVI run and post upgrade now made it Mandatory.Please update that field and Save the BP and then try to link the BP to Vendor.

In our Case,we had a Search Team as Optional at the time of CVI run but once Customer was converted into BP,we made it Mandatory and it was giving an error while linking the existing BP to Vendor.

We updated the Search term and saved the BP and then ran the FLBPC2 - Link BP to Vendor,it worked perfectly fine in S4HANA 1610

Regards,