Hi,

After creating demand in md61 and after running MRP we want system to give process order number instead of planned order number.

In short we want to skip planned order to process order conversion. We want to directing confirm the process order. Please confirm is it possible. ?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Please check the thread below. This might be of some help. Though I fully agree with Mr Mangalraj that the requirement is not standard SAP.

https://scn.sap.com/thread/2135568

Regards,

Bhaskar

former_member184655
Active Contributor
0 Kudos

Dear Sunriser,

This is not possible in standard SAP with a MTS scenario wherein for the Planned independent

requirements the system will be creating either the planned order/purchase req for the demand.

the system can never create a process/production order directly in this case.

check this link to explore more about assembly processing with production order

http://help.sap.com/saphelp_47x200/helpdata/en/41/191eb845fd11d188ff0000e8322f96/frameset.htm

Regards