Hi,

I have a requirement where I have to copy Plan cost in KP97 from one version to another. I get all the data except Planned cost. The same is required in KP98.

I have to get plan cost from KP06.

Can anyone tell me any BADI which can allow me to create one additional column on KP97 and KP98.

Also, in which database table, value from KP06 are stored?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 16, 2017 at 09:01 AM

    Hi,

    CO planning data is stored in COKP (primary) and COKS (secondary) tables. That's for totals... Planning documents are stored in the same tables, as actuals (COBK/COEP), but with different value type. Documents will be stored only if you work with integrated planning; otherwise, only totals will be available.

    Regards,

    Eli