Hi,
I am doing post installation steps for XI3.0. I have loaded the latest CIM files from SAP.
I can start the SLD server under administration-> Server Settings-> Start
However, on the next step for the data supplier bridge, under administration-> data supplierI enter True for update SLD, I enter the fully qualified host name and I enter the gateway sapgw02(same as the XI instance) for the SLD. When I hit start, the bridge stays in stopped mode.
This is the first step of configuring the bridge. I have not even gotten to the ABAP and JAVA sides. What could be causing the bridge itself not to start?
Thanks,
Chris