on 11-15-2013 1:10 PM
Hello all.
I need your help to know how to solve this kind of topic.... if possible.
I would like to fix my purchase requisitions in SNP (manually) and maintain my stock on a hand under safery stock (in one period).
When I do that, and fill a quantity in a future to finish this "period" and recover my safety stock level,,, the system automatically place a purchase requisition in advance to recover automatically my safety stock level...
there is any way to avoid this process?
in comparation, in R3, with the same requirements, when I place a purchase order /requisition in future and my stock level rise to positive,,, next purchase requisitions are going to place in the future and no orders "jump" back to cover or recover my safety stock.-
Thanks a lot for your comments.
O.
Hi Oscar,
You can make use of extended SNP Stock transfer horizon to avoid creation of receipt for an extended period.
Regards,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.