Multiple settlement assignment in CO order with RA (WIP)

Former Member
0 Kudos

Hi guys,

I need help (kind of urgent).

Here is the scenario:

I use plain CO order.

I have 2 types of costs (say direct costs [DC] and management fee [MF]) to which I want to use source structure in the settlement rule.

I also have revenue [REV] which I don't want to settle.

I use result analysis to put costs into WIP.

What I want is that costs which are not covered by revenue are go/remain in WIP till TECO than I want to finally settle the whole stuff regardless whether revenue exceed costs or not.

In the settlement rule I have only 2 assignments: for DC and MF with FULL.

Here is my config:

  1. I created three type 31 cost elements for DC, MF, REV
  2. The cost elements for DC and MF I put in the source structure.
  3. OKG2 and OKG3: I’m not sure about the settings but for the time being something else is the problem (see at the bottom). However, in OKG2 I set the “order
  4. I defined 3 line IDs for the above costs (DC, MF, REV).
  5. In OKG5 I mapped cost elements to line IDs.
  6. In OKG4 I defined the update for RA: costs to category K, revenue to category E, cost elements accordingly assigned
  7. In OKG8 for each type 31 cost element I created the WIP/WIP Settlement account assignment. With WIPR, which I can't say it's correct or not.

I posted some costs in period 1 and do the RA calculation (KKA1) and settled. Costs went to the WIP account in line with the OKG8 settings.

Then I posted some costs and some revenue in period 2. Do the KKA1 and tried to settle and I got this:

No source assignment found for cost element REV (KD560).

Which is obvious since I don’t want to settle the revenues, they can remain on the order.

When I created additional source structure assignment and put REV into it then I had this:

Debit with cost element REV cannot be settled (KD549).

I don’t want to settle this. In OKO7 the 100% validation is unchecked.

What am I missing?

In tried with both settings in OKG2: “Internal and Service orders w/o Revenue” – checked and unchecked.

(once I pass thru this I might be back with further OKG2/3 settings)

Thanks

Hungry Joe

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Joe,

I'm afraid you'll need to tackle OKG2 first.

It defines the basis for your RA (or WIP) calc.

What is the logic to calculate WIP?

Is it just the criteria of Revenue being posted or not?

If that's the case how do you determine which costs elements "generated" revenue?

Thanks,

Szymon

Former Member
0 Kudos

Thanks Szymon for your concerns.

WIP has to be calculated each time if there are costs.

Any revenue should decrease the balance of WIP. Example (each line is a period):

Period
Costs
Revenue
WIP
Settl. to Object (GL Acc.)
11000
1000
210001500500
35001500
2500

After the last revenue invoice I set TECO and settle the costs.

And I have to settle my costs to 2 different GL account so I have to use multiple settlement assignment int the settlement rule.

As for OKG2 you mentioned, I certainly overlooking something but I can't see what should I do here. Didn't you mean OKG3 by any chance?

At this point the problem is that the system requires me to assign revenue to the settlement rule like it should be settled which I don't want to do.

Thanks for help

HJ