on 11-13-2013 2:59 AM
I have created new company code with new FM area and has done all the required configurations.But when I am creating PR for Rs.1, then its showing "Commitment budget was exceeded by 1.00 INR in document item 010" although i have assigned and release the budget for said fund centre and commitment item. But this is working fine for other company codes.
Can u suggest what I miss and what i need to do now.
Dear All,
The issue resolved. It was the in the budget profile where avl control should be on release as it was on overall earlier.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear All,
This is working fine for other company codes so there might be some company code or FM area settings.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Excuse me Prem, welcome to SCN forums.
This people are trying to help you, so give more details about your problem:
prem sharma wrote:
I have created new company code with new FM area and has done all the required configurations.But when I am creating PR for Rs.1, then its showing "Commitment budget was exceeded by 1.00 INR in document item 010" although i have assigned and release the budget for said fund centre and commitment item. But this is working fine for other company codes.
Can u suggest what I miss and what i need to do now.
We need the screenshots from error, and from your report where you check the budget.
Tell us what's the name from your "new company code".
Regards.
Hi,
First of all check, if the FM objects put in the message are exactly the ones, where the budget is put on. Verify that you don't have any budget address derivation logic. Then, try and reconstruct your AVC ledger via FMAVCREINIT transaction and make the posting again.
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
1. Check the fund center and commitment item if the budget is available
2. Check the commitment items on the same fund center to know the overall budget availability
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.