I have created new company code with new FM area and has done all the required configurations.But when I am creating PR for Rs.1, then its showing "Commitment budget  was exceeded by 1.00 INR in document item 010" although i have assigned and release the budget for said fund centre and commitment item. But this is working fine for other company codes.

Can u suggest what I miss and what i need to do now.

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Dear All,

The issue resolved. It was the in the budget profile where avl control should be on release as it was on overall earlier.

Former Member
0 Kudos

Dear All,

This is working fine for other company codes so there might be some company code or FM area settings.

waldo
Contributor
0 Kudos

Excuse me Prem, welcome to SCN forums.

This people are trying to help you, so give more details about your problem:

prem sharma wrote:

I have created new company code with new FM area and has done all the required configurations.But when I am creating PR for Rs.1, then its showing "Commitment budget  was exceeded by 1.00 INR in document item 010" although i have assigned and release the budget for said fund centre and commitment item. But this is working fine for other company codes.

Can u suggest what I miss and what i need to do now.

We need the screenshots from error, and from your report where you check the budget.

Tell us what's the name from your "new company code".

Regards.

Former Member
0 Kudos

Yes,I agree, but I am unable to upload the screenshot.

I think if there is any error related to AVC.

when i run FMBV, but it shows "No budget exists - availability control not activated"

how could we check this?

iklovski
Active Contributor
0 Kudos

Hi,

First of all check, if the FM objects put in the message are exactly the ones, where the budget is put on. Verify that you don't have any budget address derivation logic. Then, try and reconstruct your AVC ledger via FMAVCREINIT transaction and make the posting again.

Regards,

Eli

Former Member
0 Kudos

Yes, It is exactly the same.

I have tried FMAVCREINIT and it shows No message in the error log.

Is there anything that I miss in the FM configuration which are concern to this?

iklovski
Active Contributor
0 Kudos

No message in error log means that the job is completed. Did you retry the posting?

Also, check how you set up the budget availability in your AVC ledger.

suma_mani
Active Contributor
0 Kudos

Hello Prem,

Check OF09 ,if it is OK,on the trace in FMDERIVE > Check which account assignments are updating while creating the PR. I mean fund center and Commitment item.

May be account assignments are differ.

Regards

Mani Kumar


Former Member
0 Kudos

Yes, I retry posting after that but same error.

In report, I can see the budget is available for the said fc and commitment item.

Former Member
0 Kudos

In OF09, it is no errors found.

I had trace on the FM derive to check and found the same account assignment which has the available budget.

If there any configuration which I miss to commit budget or for any such errors?

suma_mani
Active Contributor
0 Kudos

Hello ,

Check report FMRP_RW_BUDCON for same account assignments > Consumable budget must be available ,if not you  are not released. Send screen shot also.

Regards

Mani


Former Member
0 Kudos

We are using former budgeting and use S_KI4_38000050 to check the budget. Is is there in available budget. Due to some techincal issue I am unable to upload the screenshot, but I crosscheked again, it has available budget.

suma_mani
Active Contributor
0 Kudos

As per my knowledge try to release the same budget again. I hope that was the issue. If you find already released you may wait for experts opinion.

Regards

Mani

iklovski
Active Contributor
0 Kudos

If you are using Former, then why executing FMAVCREINIT? I though, you are with BCS... Try and reconstruct the ledger with the transactions for Former budget.

Former Member
0 Kudos

whats the tcode for that?

Former Member
0 Kudos

It is alredy released

narasimhulu_konnipati
Active Contributor
0 Kudos

1. Check the fund center and commitment item if the budget is available

2. Check the commitment items on the same fund center to know the overall budget availability

Thanks

Former Member
0 Kudos

I already said i have assigned and released the budget and it is showing in said commitment and fc