Hi folks,
The purchase requsition are getting stuck with the error "Schedule line without external number does not exist in R/3".I checked all the master data.its seems to be ok.is it related to any number range issue.
Please help.
Thanks,
Suyash
Is there a push button to push to R3? Trying pushing it and see what error appears.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Suyash,
Error is referring to Requirements Qty. and not to receipts Qty.
Please check the requirements qty. at source location in APO and in R3?
Is source list correctly defined in R3? Are the MRP Type, Pl. Sp Matl status at Source plant correctly maintained? Is Material master maintenance complete at source plant?
Regards,
Ravi
Hi Suyash, how are you?
Have you already tried note 1786322?
Cheers,
Rodrigo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.