prioritizing production using S&OP Optimizer

Jan 14, 2017 at 04:48 PM

52

avatar image

Hi ,

I have a scenario with three products A B and C.

Now my objective is, In my manufacturing plant only A and B will be produced in Week 1, Product B and C in Week 2. How can I achieve this with Supply Optimizer.

I am using IBP version1608.

Regards,

Sourojit

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
avatar image
Former Member Jan 16, 2017 at 11:12 AM
1

HI Sourojit,

You could achieve this in two ways in the current release with optimizer.

  • Make capacity consumption rate as timebound.
  • Add a dummy resource for each PV and adapt the capacity as per your weekly needs.

Based on how you are integration production version from ECC system( manual or automated), you could take any of the above approach.