Dear Guru's,

I am very much new in Project system Module and I have an issue regarding Project Release.

My problem is, i have release header WBS, Header Network and activity without releasing the project definition and

I also confirmed some of the activity. When I am going to release the project definition system shows an error as

Status PRBA is not allowed (PRJ TR/MU/UK/A25/0034)

Message no. BS043

Diagnosis

User status 'PRBA' has reference number 20. In the current object

status 'PRJ TR/MU/UK/A25/0034' the reference number of a status must be

at least 45.

Though i have change the user status from 20 - PRBA to 45 - PRAC.

I dont understand why system remembers the previous status although i have updated the user status.

Please Help me on this issue.

Thanks in Advance