on 10-07-2005 2:13 PM
hi friends
i have problem and looking for your valuble help. my problem is
client year starts from july 1st2005 and ends on june 30th 2006
where we cannot use standard sap year .
client week start from 1/07/05 irrespective of the day .
there week start from sunday to sunday
ex if the 1st of july starts on friday there first week starts from friday 1st july and ends on sunday 3rd july . and again 2nd week starts from sunday to sunday and so on
same with quaterly . there qauterly also starts from july -september would be their 1st quater and oct -dec would be 2nd quater so on .
is there any possiblity to this . how this can be done . and where this ahas to be to satisfy client requirement . hope you all will look into it and give ur suggestion . all suggestions are appreciated and rewarded . thanks for your help
Veda Sri,
Since the topic is under Business Explorer i am assuming you what to see this in reports.
You can compute this by using Client's calendar, if your client doesnt have R/3 then the factory calendar should be maintained. Once you have the calendar you can use some standard function modules to compote week, month and quarter dates these dates can be passed on to the variables to get the desired results
Hope this helps..
Sridhar.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.