Strategy 11

Former Member
0 Kudos

Hello ,

I am using strategy 11 for finished product as well as dependent BOM part also. For both MRP type is PD and mixed indicator 2 ( Gross requirement planning ).

But After MRP run system generates Planned order only for Finished product. system generate exceptional message as '' 40 coverage not provided by Master Plan '' for dependent bom parts

is there any solution for above??

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Caetano & Anupam ,

Thanks for reply. Problem solved .

you are correct strategy 11 only work with PIR. So did the following setting ,

For finished product : Strategy 11 , mixed indicator 2 ( gross requirement planning )

For Bom parts ( Dependent req) : Strategy 11 , mixed indicator: 1 ( planning with final assembly )

then i used Sloc MRP indicator 1 for all storage location other than Production storage location for all BOM parts.

These Setting generates Gross requirment planning for Finished product , and automatically transfer gross requirement to BOM parts as i maintained the Sloc MRP indicator to all storage location other than production storage location. Here Production storage location would work as work in process storage location.

Best regards,

Rahul

Anupam1143
Active Contributor
0 Kudos

Hi Rahul,

If you are using the Gross requirement planning for both header and component then you need to enter the PIRs for both parts, then only system generates procurement proposals. Remove the strategy group 11 from BOM component and then execute MRP.

Then it will generate procurement proposal.

Regards,

Anupam Sharma

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Did you check if your component was actually planned by MRP? Take a look on transaction MD05 and check when was the last planning run for this component and if there was any error message. If you are running MRP in transaction MD03, for example, only the header material will be planned, so you should try to run MRP for the entire plant using report RMMRP000.

I suggest you to take a look on the following blog for details:

https://blogs.sap.com/2015/11/16/what-can-i-do-if-mrp-does-not-plan-a-material/

Regards,

Caetano

UmeshMali4994
Active Contributor
0 Kudos

Hello Rahul,

If possible share your Md04 and Md61 screen shot to understand your requirement much better.

As per standard process it will create planned order for finished product as well as semi finished product.

Please check the below point:

1. Please check the Planning file for Header material and Component.

2. You have set the proper Procurement type for component.

3. You can Re run the MRP with Planning Mode: 3.

Please check and revert

Regards

Umesh Mali

Former Member
0 Kudos

Hello Umesh ,

I already cross checked above suggested point. PIR requirement type is BSF. I am using strategy 11 first time .

please check following screen shots.

one-of-the-child-part.png

header-material.png