on 10-25-2013 7:11 PM
Please could somewhone help me to understand:
- Why KOAR settlement is included in RPSCO table, but KOAO & KOAL are not?
Also, is there somewhere some description/documentation available on what is in principle included into RPSCO Table & wahts is not?
Many thanks in advance,
Daria
Hello Daria
this is all explain in note 51971
in short ..
settling from outside a project hierarchy to an element within the project hierarchy,
cost reporting for the project will therefore not show these settlement value.
I hope this helps
ger
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.