HI all.

When you make GR there are two fields in document to enter a date "document date" and "posting date": can it be customized to have into account one of them, is it always one of them by standard, maybe it depends on value of field "Price Determination Date Control"?

User is complaining because sometimes it differs GR price from vendor invoice when ERS is generated because there are 3 days difference between delivery date from vendor to our plant and in contract is told that prices will be defined during supplier delivery date (incoterms EXW), not at receiving.

Thanks!!!!

Accepted Solutions (0)

Answers (1)

Answers (1)

Prasoon
Active Contributor
0 Kudos

Hi,

   Yes, you are right.

    The price determination date can be controlled by 'Price Determination (Pricing) Date Control' in info record. If you want the price determination date as delivery date, maintain Price Determination (Pricing) Date Control as 3 as shown below.

Please check the link: http://scn.sap.com/message/10804382

Regards,

AKPT

Former Member
0 Kudos

Hello AKPT. Thank you for the fast answer.

I tried to populate this field with value "3" in schedule agreement but even if it is new, it is as no editable. Even if in info record has been entered with value "3".

How can I populate it with value "3"?

Many thanks in advance and best regards.

Prasoon
Active Contributor
0 Kudos

Hi,

   Maintain the pricing date control at info record level.

Regards,

AKPT