on 10-18-2013 2:21 PM
Hello,
here is an example of our problem:
we have a goods receipt in a SAP WM-storage bin:
Goods receipt with 10 ST in MM.
But in WM I want to get 5 ST in storage type 110 (pre-allocated stock, gets booked out of stock directly after goods receipt) and 5 ST in storage 001 (high rack warehouse, stays in stock here), because the material is a pre-allocated stock (LT51, we need 5 ST directly on field installation).
Is it possible to split the TA or Transport requirement (not always, but when the material has an entry in T310(LT51, pre-allocated Stock) ).
Is there an user-Exit?
Thank you very much.
Hi
Please check the user exit. you can write your own palletization logic in this
MWMTO004 EXIT_SAPLL03A_005
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello, do you mean MWMTO007? I think that MWMTO004 is not correct (Own stock removal strategy).
I need a an user-exit that helps me by goods receipt (placement strategy). The objective is to get a goods receipt with 10 pieces. In WM I want to put 5 pieces to storage type 001 and 5 pieces to storage bin 110. But I have to do this assignment dynamically (entries in Z-table).
Thank you very much, I hope anybody can help me.
HI,
This is possible, manually, when you create the TO for putaway.
http://help.sap.com/erp2005_ehp_06/helpdata/en/c6/f83fbe4afa11d182b90000e829fbfe/frameset.htm
If you want to automatize the process I think you should use a user exit at the creation of TO
Best regards
Claudio
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.