on 10-15-2013 12:51 PM
Hi Experts
please help me out by this situation where we made one sales order for 100 Item and every line item is trading Goods and having 02 availability check into
material master, now when a new purchase has come into any item out of 100 item and i am going to check availability check is not happening , even
Material GRN is happened into project(special stock) + wbs Combination.
Rgds
Pankaj Agarwal
Were the stocks updated with special stock indicator "Q" which is intended for PROJECT STOCK ??. Also share your settings of OVZ9 for 02/AQ
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pankaj
At the schedule line level, please check whether schedule line category is activated for availability check . If Yes, then pl check at the item level, in the account assignment tab, have you maintained the correct WBS element for which stock is maintained?
Rgds
Pronojit Gupta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.