ML two error dependent

Former Member
0 Kudos

in my plant 1100, MMRV shows current period sep and previous period Aug. in CKMLCP we already run June closing, I try to run July ML closing, it says error:

You cannot perform price determination in period 007 / 2013

Message no. C+712

Diagnosis

You want to perform single-level material price determination in valuation area 1300 for period 007 in fiscal year 2013.

You can only perform single-level price determination in the previous period or the current period.

++++++++++++++++++++++++

so I run CKMLCP for Aug. for plant 1100. i hit another error:

Carry out period-end closing for material 11001008  in the previous period

Message no. C+805

Diagnosis

You want to perform single-level price determination for material

11001008

with valuation type  in valuation area 1100. You have entered the period for which the price is to be determined, but you have not yet completed period-end closing for the material in the previous period. The status of the material in the previous period is Period Opened.

Price determination indicator 3 requires that you perform single-level price determination (and possibly multi-level price determination) each period as well as the corresponding closing entry. This is necessary even if you have not entered any actual data for the material.

System Response

The system does not allow single-level price determination for the specified material.

Procedure

You must perform single-level price determination (and possibly multi-level, as well) and the closing entries for the previous period before proceeding

++++++++++++++++++++++++++++++

so should I go back to run CKMLCP for July, then I will hit 712 error again, what should I do?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi...

First, You should analysis the cause that Material ledger’s closing job(t-code : CKMLCP) don’t carry out closing job for material 11001008 in period 007 / 2013 through job log occurred
at each ML closing step.

Second, To carry out closing job for material 11001008 in period 007 / 2013 , Refer to Note 361236’s solution.