As i am creating a BW estimation model I have put the following effort for complexities for differnt tasks. Please suggest if you think the estimation should be differnt to what I have estimated as I am a rookie in these area.

Complexity(in Man Hrs)

Type High Medium Low

Set up Technical Enviroment 16 12 8

Define Source System 24 18 11

Define Extract Structure 24 18 8

Define Info Object 5 2 1

Data Staging 16 12 8

Transformation and Mapping 24 16 8

Build/Activate Data Targets 16 12 8

Define/Update Update Rules 24 16 8

Reports 24 16 8

Process Chains 24 16 8

Thank you so much for your help in advance.