IBP Planning level activation error

Former Member
0 Kudos

HI all,

I am a bit rusty on the basics of IBP as I have not had any IBP projects for a while.

We now have a POC System with RDS content loaded. The specific industry requires us to plan per material batch.

What I have done was the following (Actual names may differ as per screenshots):

- Create New Master Data Types:

- U05BATCH (Simple) with basic attributes - (BATCHID, BATCHNUMBER)

- U05PRODUCTBATCH (Compound) with all the batch characteristics as attributes - (BCHMINERALCONTENT, BCHMINERALGRADE, BCHSTATUS)

When I activate the planning area with the master data it all works. Everything is fine.

I then also want to create the planning level for (PERIOD | PRODUCT | BATCH).

For this I create a planning level and add: time profile with ROOT = Monthly. U05BATCH with ROOT = BATCHID. U05PRODUCT with ROOT = PRODUCTID. U05PRODUCTBATCH with no ROOT.

As seen in the attachment: perprodbch.png

When I now try to activate the planning area I receive an error as seen in the error log attached: error-on-planning-level-activation.txt

I have also attached the two newly created master data types:

u05batch.png

u05productbatch.png

Please let me know what I am missing here.

Thanks and Kind Regards

R.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi, Just to give some clarity.

I resolved the problem. The reason the planning level activation failed was because there was no key figure linked to this planning level.

To resolve the problem I created a Dummy Key figure TESTPERPRODBCH which is stored at the PERPRODBCH level.

Reactivate, it wont work on the first activation however, it will give an error without details. Just reactivate again. It will work the second time.

Regards

Ruan.

Answers (1)

Answers (1)

Former Member
0 Kudos

I Apologize, wrong error log. here is the correct one.error-on-planning-level-activation.txt