Dear experts

I have a requirement when the PRT moves fro one cost center to another they need some kind of approval like once it get the confirmation from Plant A

with responsible person it can be shifted to Plant B , in the sae way I need it for Resources too.

Secondly when  & why do we exactly need to create the PRT equipment from Material what is the logic behind it ?

Is there a standard way in SAP we do this ?

Please help me to get understood.

Thank you

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

When you track the PRT goods movement with stock & to track the Maintenance history, then you should go for creating PRT as material by having serial number profile, subsequently equipment etc.,

Regarding Approval, you may not achieve it in standard. Based on the field changes like Maintenance Plant, Cost center, etc., you can develop a custom program to trigger the workflow to respective people.

Also you can use User Statuses to control business transaction. By which, once after approval only, that equipment can be used at target location for any SAP entries.