Question about CHARM transport between different systems

  • SITUATION;
    • We have a complex enviroment, with ECC, BW and SCM in place
    • We have several projects running at the same time, that will have a GO LIVE together
    • We have dependency between transports, ECC transport ED1XXXX should come before SCM transport SD1XXXXX, right now we are importing ALL transports from ECC first, then the other systems, but this is not the expected situation, we are not efficient.
  • QUESTION;
    • We want to know if one CHARM can orchestrate the transports between the whole landscape, sequencing the transports to all the systems involved.

Thanks!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Oct 10, 2013 at 10:34 AM

    Hi Mario

    You should have one project with all landscape like ECC SCM etc which will help in this use case

    also you can create a single change request with multiple change documents which might help you to cater these needs

    check my blog below

    http://scn.sap.com/docs/DOC-46777

    Hope it helps.

    Regards

    Prakhar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 10, 2013 at 02:14 PM

    Hi Mario,

    QUESTION;

    • We want to know if one CHARM can orchestrate the transports between the whole landscape, sequencing the transports to all the systems involved.

    In ChaRM we able to create the single project for whole landscape but with same type of landscape like ( 3 system in single project, 4 system in single project ..) like mentioned by Prakhar

    In Rfc the scope assigment block need to select the individual landscape only( not able to select the whole landscape in single change document, because every PRD system having individual ibase), if u want to create the change document for ECC ,SRM ... need to select the two change documnet and select the ibase for each system like ECC ,SRM...

    So the Single Change document will handle only the individual landscape TR's movement, not able to handle the whole landscape TR's movemnet in the single change

    So if you having dependency between the landscape needs to handle by the team, like first execute the ECC change document and then handle the SRM landscape CD.

    Rg,

    Karthik

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Prakhar Saxena

      Hi Prakhar,

      In Normal Change:

      we have option like one Rfc with one change document and multiple transports.( like ECC, SRM, ..),during TR's creation it will show all the development system ( like ECC, SRM..) but during TR's import in normal change we need to go to the maintenance cycle and schedule the TR's to the respective system ( ECC-QAs separately , SRM - QAS separately..) So NC will not take care of automatic import between the whole landscape depend upon sequence in the same project. it will take care the particular system like ECC-QAS sequence only. we need to trigger the TR's manually in the MC depend upon the dependency between the ECC or SRM landscape. which is first. Please correct i am wrong

      But Mario looking for transports between the whole landscape, sequencing the transports to all the systems involved using ChaRM -As i know this is not possible in ChaRM to import the transport in sequence between the whole landscape with automatic workflow.

      In Urgent Change:

      Any option in urgent change like using multiple transports option, Normally the urgent change allow to create the one customizing and one Work bench. not tried this option for combined landscape project.

      Rg,

      Karthik