Whenever user made changes on the maintenance order, example ;- add new operations line, the schedule start and schedule end will be changed and PR delivery date will take this date as a new delivery date.
I have requirement from user , if the user made a changes on the maintenance order operation, the date in maintenance order should not be reflect to PR delivery date ?
can it be done by configuration or need customizing ?