Hi masters,

I´m following this post: http://scn.sap.com/message/14195529

to change my time evaluation period from 26th to 25th next month.

time schema is ok, the balances are calculate ok, but in pt_Bal00, it´s showing the balances from previous month.

My employee is active from 1st of March but time evaluation is calculated from 1st of April (to 25th of the same month)

I re-generate RPTIME00, SAPFP51T, RPTEDT00 and RPTBAL00, but for example if I have a balance of delay calculated for day 4 and April 5, and the report pt_bal00 is showing me for the 7 to March 8.



I deleted the cluster B2, recalculated times and relaunched the pt_bal00 and the same.

internally, I see that 1st of April, in ZES is 7th day (logically, because first day of time evaluation is 26th of March)

Any idea? thanks a lot.

Attachments