Hi Experts, Background: 1 annual system control project budget, the project total investment of 100, the annual budget allocation, this year, next year, 70, 30,. 2 this year, there has been a procurement application of 70, the next year, a procurement application occurred in 30. 3 would like to purchase the next year to apply for 30 converted into a purchase order, the date of delivery of the date of this year.

Question: reference to the next year to create a purchase order purchase orders, delivery date changed to the date of this year, to save the purchase order is a reminder of this year's annual budget. Experts, this situation should be how to deal with?