Hi,
I have created production order wherein system do not scheduling production order correctly.
1. There are two workcenter in routing with processing time 8 hr/unit.
2. Capacity of each workcenter is 8 hr.
When I creating order for say 2 unit, sytem should show start date 03.10.2013 (Current date Scheduling Type) & End date should be 06.10.2013.
But in my case its showing End date as 03.10.2013 only.
Setting in OPU3 -
1. Detailed scheduling with Genrate Capacity reqs.
2. Adjust Scheduling - Adjust basic dates,adjust dep. req, reqmts to operastion date
Could anyone please helpout.