on 10-03-2013 9:33 AM
Hi,
I have created production order wherein system do not scheduling production order correctly.
1. There are two workcenter in routing with processing time 8 hr/unit.
2. Capacity of each workcenter is 8 hr.
When I creating order for say 2 unit, sytem should show start date 03.10.2013 (Current date Scheduling Type) & End date should be 06.10.2013.
But in my case its showing End date as 03.10.2013 only.
Setting in OPU3 -
1. Detailed scheduling with Genrate Capacity reqs.
2. Adjust Scheduling - Adjust basic dates,adjust dep. req, reqmts to operastion date
Could anyone please helpout.
Hi,
Please cross check below points for your scheduling issue.
1. Workcenter formula - Use 'Test formula' function in workcenter scheduling tab pabe and do the scheduling test in workcenter itself. It'll ensure the workcenter formulas are correct.
2. Update the material master with routing time by using tcode CA97. This is a standard SAP procedure to avoid any scheduling mismatch.
3. In OPU3, have you selected the correct plant, order type and especially production scheduler.
Still if you find any issue, revert back.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Rajesh,
Check if the formula assigned in the scheduling tab page for processing field has the check box
included for scheduling,press the "I" key to check this setting.now if you are getting the duration
properly when you manually test the values in the work center and not getting the same during
planned order/production order processing means check if the control key assigned has the setting
for relevant to scheduling.
Assuming the control key has the setting included for scheduling,and still the system is not
calculating the operation timings means,i would suggest you to remove the work center in the
respective operation, press enter then reassign the work center,save the data and check once
again.
Regards
Mangalraj.S
Hi Dharma,
I have already check all this basic setting which required for scheduling operation.
I have used standard control key PP01 for all operation wherein Scheduling tick mark is activated.
In OP21, Formula definition - I have used SAP standard formula SAP002 (Prod: Machine time) wherein tick mark is activated for "Allowed for Scheduling" and same formula SAP002 has assigned in Scheduling Tab under Processing formula in both work Center.
Dear Rajesh,
Still I'm unable to conclude the reason,but one final try can you please delete the particular
operation, enter the same data -->work center--->operation timings in a new operation save the data
and check by creating a new planned order or production order or else go for scheduling in the
routing level itself,by selecting this menu path-->Extras--->scheduling--->schedule--->scheduling
type--->lot size = 1 and check the results.
Regards
Mangalraj.S
Hi,
Please check the following:
1. Check if your scheduling formulas are correctly maintained at work center level
2. Ensure no reduction is carried out by looking at the first tab in the order
3. Ensure no parallel sequence is maintained for the operations
4. Try to simulate with higher quantity and have a closer look at the minute level also and come back with your response.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1. In work center, Standard value key SAP1 is assigned & standard SAP formula SAP006 & SAP002 maintained properly.
2. As there Float period is zero then no issue of Reduction. But even I have checked that reduction is not carried out.
3. There is no parallel sequence maintained for operation.
4. I have created order with unit 5000 to 10000 but even Start date & End date is same that is current date 03.10.2013
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.