versions in mc87 or in md61

Hi, as I understand, when we create ind req, we need to create in inactive versions in mc87 or in md61 and when we transfer we need to transfer in mc74 in active version. please explain why we need different versions in mc87 or in md61. what is the practical use of these versions while creating. does it mean, the requirements (example) from 01.10.2013 to 30.10.2013, should be one version and next month should be another version, is it like that. do we need to combine expected requirements from different customers for one period and put it as one version or is there any use?. can we use same functionality for long tern planning too also? if so how to use the same. please advise.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Oct 02, 2013 at 01:17 PM

    Hi Raju

    Different versions allow you have different scenarios on your planning, for example, one optmistic and on reallistic. You can flexibly choose which version shoul be used.

    Also, it allows you to work with different sceanrios on long term planning.

    You can use, for example, transaction MS64 to copy planning values between versions.

    It is not practical and it is not a common practice to separate each month on a different version.

    BR

    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 02, 2013 at 02:29 PM

    Hello Raju,

    with your question you touch two different planning levels in SAP, the sales and operation planning (SOP, T-Code MC..) and the Production planning (T-Code MD..). These two levels are separated. You can do capacity checks and optimistic and pessimistic senarios in the SOP and the production planning. That is why there are verions in both of these levels. When you are fine with the result of youre SOP you hand over the quantities of the "best" version to the production planning with mc74. Perhaps you want to do more checks, more detailed checks then in SOP, so you can copy to an inactive version in production planning and run one or more szenarios in long term planning.

    You can use two active versions in production planning to handle two different customers, but there is no connection between the customer code in the order and the planning version, so its not garunteed that the reduction of independant requirements ist correctly.

    Greetings

    Bjorn

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.