09-30-2005 12:18 PM
Hi
I need to know what is the inbound process code for work centers trasnfer through ALE
Thanks In advance
Sree
09-30-2005 1:02 PM
There is no ALE for a work center (Release 4.6B), but there is a report to up- and download the workcenter. I have to search this report.
Kind regards
09-30-2005 1:34 PM
Hi Matthias,
I have created an outbound work center using the Tcode POIM and message type LOIWCS, and the status of the created IDOC is 03. that means idoc is created and when i checked in the inbound side. the status is 56, Desc. Partner Profiles not defined.
So,i think based up on the above evidence there is an ALE technique to transfer work centers.
PLease correct me if I am wrong.
Regards
sree
04-12-2006 5:29 PM
Hello.
I'm trying to send work centers by idocs as well.
May you tell me the selection criterias I have to give to select work centers ? Actually, I just choose :
- "complete" transfer mode,
- "work center for" radio button
- and fill the plant I want.
But unfortunately, no work center is selected and 0 idoc is sent whereas, I've checked that at least 80 work centers should be concerned.
Do you undestand why ? Shall I set the change pointers ?
Thank you in advance for your answer.
David.
06-15-2006 12:26 AM
I have same situation as Sree has described. Is anybody have done work center ALE successfully? What is the process code for inbound IDOC? I would greatly appreciate your help.