subcontracting components using MRP Areas

Hello

When PR's are generated for subcontracting components using MRP Areas, the source of supply is not being populated on PR based on the quota arrangments . There is a SAP Note 505667 which looks like is solution for this. Any one have any idea on this? what are precaution that needs to be consider before implementing this note?

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Sep 29, 2013 at 06:07 PM

    Hi John,

    Better to raise OSS and discussed issue with SAP, before implementing the note.

    Regards

    Vikrant Hande

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 30, 2013 at 07:35 AM

    What does the note say?

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 30, 2013 at 01:16 PM

    Hello

    Note 505667 is the solution for this issue.

    Precautions and possible side-effects are fully described on the note long text. See below:

    You can reverse Note 406672 as described in the attached correction

    instructions. This also allows the quota arrangement in the storage

    location or SC MRP area. You should only use the modification proposal

    if the quota materials in the storage location or SC MRP area are only

    planned a using external procurement. If you are using a special

    procurement key for the quota materials in the storage location or SC

    MRP area, this may be overridden by the modification (undesired side

    effect when using the quota arrangement at plant level). Therefore, the

    modification proposal deactivates the quota arrangement in the storage

    location and SC MRP area if you want to procure using the special

    procurement key 'Stock transfer from plant to MRP area'.

    The modification does not take other special procurement keys into

    account and the procurement using quota arrangement overwrites these.

    Page 2

    Before implementing such a modification, you must consider the conflicts

    and side-affects concerning the quota quantities that are not updated

    separately for the different MRP areas.

    A recommended alternative for the modification: We recommend that you

    only plan materials with quota arrangement in the plant MRP area.

    Materials without quota arrangement can of course be procured without

    restrictions in the storage location or SC MRP areas.

    BR

    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.