Former Member

identifying planned order

Planned order in rrp3 on 10 th oct showing quantities 500 and on On 15th October quantity is 500

Forecasting given for 500 nos on 29th September

another Forecasting given for 500 nos on 5th october

The problem is how do i identify which " planned order " is attached (pegged with) which "forecasting " ? ? ?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 01, 2013 at 09:59 AM

    Hi Rahul,

    In product view you need to activate either dynamic or fixed pegging for this.

    Then when you plan, in SNP CTM has the capability to generate fixed as well as dynamic pegging, whereas Optimizer can only generate dynamic pegging.

    Once receipts are generated by planning engine, you can go and check in pegging overview tab of product view (RRP3).

    Rgds

    Sourabh

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 01, 2013 at 11:57 AM

    Hi Rahul,

    You can identify the linkage through Pegging relationship.

    BR

    Thamizh