on 09-26-2013 11:53 AM
Hello all,
i have a problem in MIRO.
i am using item type as planned delivery cost in miro.
in the details tab, in Unpl. Del. Csts field i am entering an amount and its adding to balance on top.
i copied that balance and pasted it in amount, document balance became zero.
but when i simulate, i am getting amount as zero for unplanned delv cost.
for the account 334100 the mount is coming as zero , but i entered as 500 for unplanned delv in details tab. so as its coming as zero below balance is not becoming zero.
I checked OBYC settings but its fine.
Please help.
Hi,
Account type K for vendor,S for G/L accounts and M for material.You Invoice screen have Debit 908.13,Credit 1408.13 and Balance which need to be entered is 500.You are not getting any error message on invoice posting as tolerance limits set for tolerance keys (DQ,PP,VP,PS and AP etc)for your Company code in t.code:OMR6.
But you can post Unplanned Delivery Cost in t.code:MIRO by selecting "Subsequent Debit"
Regards,
Biju K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
anupam,
the amount i entered in the unplanned delivery cost is not filled in the last item, so the balance is not becoming zero.
Regarding that line,
for PO i have taken for the above screen shot i am getting last line as handling charges and im expecting 500 given in unplanned delivery cost but for other PO's iam not getting the handling charges entry also.
can you tell me what can be the problem.
Ujwal
Dear Ujwal,
Please check below links if it helps you
http://scn.sap.com/thread/1154484
http://scn.sap.com/thread/3311202
Regards
Anupam
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.