Shelf life planning in CTM SCM 5.0

Hi Guys,

Is there any  CTM planning parameter for shelf life planning in SCM 5.0 ? If so pl provide the same.

BR

Thamizh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Sep 26, 2013 at 01:32 PM

    Hi Thamizh,

    SCM 5.0 CTM does not consider shelf life.

    In SCM 7.0

    CTM can consider shelf life constraints in a restricted way (for example, CTM does not consider shelf life propagation).

    I hope this gives insight.