Revenue budget monitoring through PS

Normally we use PS for capex budget monitoring and control. Please guide me if we can use it for revex monitoring in the similar way ?? Any difference ?? What I can think of is only of carryover .... i.e. Contrary to capex, there is no concept of carryover in revex ....

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Sep 26, 2013 at 11:01 AM

    There is planned revenue on a project which can come from assigned Sales Orders or you enter it directly in PS. This is similar to planned costs. But there is no such thing as a Revenue Budget.

    On the cost side you have planned costs and budgets which are 2 different sets of values. On the revenue side you only have planned revenue.


    What business requirement are you trying to meet?

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Yes, you can use PS budget availability for any costs. There is no functional difference in PS Budget Availability as to why you are spending money (either Capital Expenditures or Operational Expenditures).

      Carry over is part of the business budgeting process. There could be carry over from year to year on a opex spend.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.