Planned Order without PDS

Hello Gurus,

I want to generate planned order without PDS . So what i am thinking is send the toplevel product with inhouse production (without any PDS) . So when i run CTM/Heuristics will it generate planned orders still .

If yes What is the need of PDS .

Regards,

Abhinav

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Sep 26, 2013 at 04:31 AM

    Hello Nick,

    You are right. Heuristics creates Planned orders without a Source of Supply when a SNP PDS does not exist. A PDS will have BOM information, Recipe & Resource.

    So this Planned order will not generate Dependent demand on the Component, No resource loading.

    Trust this helps in answering your question.

    Thanks,

    Chandra

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 25, 2013 at 09:51 PM

    Hello Nick,

    Not sure if I understood correctly your doubt.

    Well, it seems CTM or heuristic will create the planned orders without PDS for the header product. The need of the PDS would be to plan the components if existent, and to create a source for them.

    Regards,

    Michel Bohn