on 09-25-2013 11:01 AM
Hello experts,
In CJ20N I want to delete the Measurement Method which automatically appeared within the "Progress" tab, this is happening in the testing environment which is copied from the production environment, while in production system there is no Measurement Method in the WBS element.
When I tried to delete the Measurement Method which is not wanted, I can delete it but after saving the change it is still there.
Please let me know how to delete it.
Thanks
Have you maintained any configuration in Project System - Progress - Progress Analysis that is different between the 2 systems?
Look particularly at Define Measurememt Method as Default Value.
That configuration is where the Progress tab on the WBS element comes from.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Danny,
Do you mean that you want to hide the "Measurement Method" area in Progress tab.
Best Regards,
Kim
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Danny,
I am not sure but I guess your requirement would be met by appropriate customization using OPSG regarding deletion of activity/components.
Regards
Eugene
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ranu,
Thanks for your quick response.
I checked OPSG, it does not relate the my problem. The Measurement Method is on the WBS element level, in OPSG the setting is not for WBS. I checked the configuration in OPSG between testing and production system, they are exactly the same, but the issue only is in testing system.
Do you know which table stores the Measurement Method & Progress version for a WBS element? I checked PRPS but they are not there.
Danny
Hi Danny,
Project versions - These are basically snapshots of a project at different stages of a project. Based on how the system is set up, a version could be created every time the system status of a project object is changed, for example. Or, you could manually create a project version in transaction CNS41 or the like. You could create a version with a key and then you could compare the different snapshots of a project against each other or against version 0 (operative project).
Progress Versions - These versions are used for carrying out Earned Value Analysis and other measurements against project progress based on POC, etc. Progress version is controlling area specific and defines the control data for POC and earned values. It is mandatory to maintain progress version along with method of calculation. The system records progress analysis data in the progress version. That is why you can get the result only if you maintain it in the progress tab of WBS.
Hope it is clear now.
Regards
Eugene
Hi Ranu,
Thanks for your explanation, but I didn't maintain information in the "Progress" tab, the Progress Version get automatically assigned in the Progress tab. this is not correct and I want to delete it.
Things are getting worse as I see all my projects in this Controlling Area are having this Progress Version.
Not sure why this is happening.
Hi Danny,
when you execute report CN41, just go to "Change DB profile ( CTRL + F3) " option and click on Version data. Then you can enter Project definition and execute the report. You will be able to see report with Project versions showing current data. After this you can go to option Extras/Environment-> Delete Project versions.
Please try this and I hope your issue will be solved.
Regards
Eugene